How to practice topic:construction-management

Attempt a question, record the concept and assumptions, then check the available answer. Rework mistakes after revising the relevant concepts. Topic tags can overlap; review the question context.

Questions 1–10 of 32. Imported answers require independent review unless marked reviewed.

Topic practice 32 questionsPage 1 of 4

Question 12

Open question
ARMCQ1 markNeeds review
An earthquake originates at ______________.
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 26

Open question
ARNAT1 markNeeds review
For a computer lab, a set of furniture has just been purchased at the cost of Rs. 8,50,000. The useful life of this furniture is 8 years. If the annual depreciation rate is 15%, then the salvage value of this furniture (in Rs.) is __________ (rounded off to the nearest integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 41

Open question
ARMSQ2 marksNeeds review
Which of the following is/are listed within the responsibilities of Council of Architecture (CoA) as per the Architect’s Act 1972?
Your answerSelect all correct options. You can choose more than one.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 46

Open question
ARNAT2 marksNeeds review
A construction project consists of 7 activities. These activities, their connecting events, and the three PERT times (optimistic, likely, and pessimistic), in days, are listed in the table below. The project starts on 27ᵗʰ July 2026. Assuming no holidays for the entire duration of the project except 15ᵗʰ August 2026, the expected date of completion of the project will be __________ August 2026 (mention the date in integer).
Activity
Connecting Events
Three PERT Times (in Days)
P
1 → 2
4 – 6 – 8
Q
1 → 3
5 – 6 – 13
R
2 → 5
6 – 8 – 22
S
2 → 3
8 – 11 – 14
T
3 → 5
2 – 4 – 12
U
3 → 4
4 – 8 – 18
V
4 → 5
5 – 7 – 15

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 54

Open question
AR-B1MSQ1 markNeeds review
Which of the following statements is/are correct with respect to temporary structures during construction?
Your answerSelect all correct options. You can choose more than one.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 27

Open question
ARMSQ1 markNeeds review
Which of the following is/are likely to be caused by an earthquake?
Your answerSelect all correct options. You can choose more than one.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 29

Open question
ARMCQ2 marksNeeds review
Match the following items of work in Group-I with their corresponding units of measurement in Group-II.
Group-I: (P) Honeycomb Brickwork (Q) Steel Reinforcement (R) Brick on Edge (S) Earthwork in Excavation
Group-II: (1) Running Meter (2) Cubic Meter (3) Square Meter (4) Kilogram (5) Number
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 34

Open question
ARMCQ2 marksNeeds review
In order to achieve the static equilibrium of the see-saw about the fulcrum P, shown in the figure, the weight of the Box B should be ________________ kg, if weight of Box A is 50 kg.
Diagram for Architecture and Planning question 34

Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 46

Open question
ARNAT2 marksNeeds review
A construction project consists of four activities. The duration, relationship and cost parameters are given in the table. The indirect cost of the project is INR 500/- per week. If the project has to be completed by 12 weeks, the total project cost will be, INR______________. (Answer in integer)
Activity
Immediate Predecessor Activity
Normal Duration (Weeks)
Crash Duration (Weeks)
Normal Cost (INR)
Crash Cost (INR)
P
Nil
8
5
20,000
26,000
Q
Nil
5
2
30,000
33,000
R
P
6
4
40,000
52,000
S
Q
4
3
10,000
13,000

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 44

Open question
ARNAT2 marksNeeds review
At present, the cost of a new office equipment is 50,000 (in Indian Rupees). It has 15% salvage value after a useful life of 5 years. Using straight line method of depreciation, the book value of the equipment 3 years from now, in Indian Rupees, will be ____________ (in integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer