Question 38

Open question
ARNAT2 marksNeeds review
Fee of contractor for a project has the following provisions • Basic fee = 15% of actual cost of work incurred • Bonus = 20% of savings from estimated cost of work • Penalty = 20% of cost overrun If the estimated cost of the project is Rs. 60,000, and the actual cost is Rs. 70,000, then the total fee of contractor in Rupees is ________

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 40

Open question
ARNAT2 marksNeeds review
The optimistic, most-likely and pessimistic time for developing a new product are 12 months, 15 months and 17 months, respectively. Calculate the expected time in months.