Question 35
Open questionARMCQ2 marksNeeds review
Match the planning techniques in Group-I with their salient features in Group-II.
Group-I
P. Land pooling
Q. Action Plan
R. Land sharing
S. Transfer of Development Rights
Group-II
Assigning specific task on a short time horizon
Assembling privately owned land parcels for development
Agreement for reallocation of land between occupiers and owners
Assigning specific task on a long time horizon
Incentive based voluntary shifting of FAR of a plot to another plot
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 44
Open questionARNAT2 marksNeeds review
In year 2001, a district with 4,000 manufacturing jobs had a 10% share of total manufacturing jobs within the state. In year 2011, the state recorded 15% drop in manufacturing jobs whereas share of the district in total manufacturing jobs within the state increased to 15%. Additional manufacturing jobs created in the district between year 2001 and 2011 is ________
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 46
Open questionARMCQ2 marksNeeds review
Match the planning tasks in Group I with the tools of analysis in Group II
Group I
(P) Population projection
(Q) Regional resource allocation
(R) Trip distribution
(S) Design of water distribution network
Group II
Input-Output Analysis
Hardy Cross Method
Cohort Analysis
Gravity Model
Moving observer method
Your answerChoose one option.
Log in to check the answer