Question 5
Open questionCEMCQ1 markNeeds review
Gypsum is typically added in cement to
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 6
Open questionCEMCQ1 markNeeds review
The direct and indirect costs estimated by a contractor for bidding a project is ₹16000 and ₹2000 respectively. If the mark up applied is 10% of the bid price, the quoted price (in ₹) of the contractor is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 6
Open questionCEMCQ1 markNeeds review
Strain hardening of structural steel means
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 8
Open questionCEMCQ1 markNeeds review
Seasoning of timber for use in construction is done essentially to
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 9
Open questionCEMCQ1 markNeeds review
In case of bids in Two-Envelope System, the correct option is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 30
Open questionCEMCQ2 marksNeeds review
Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y’s bid price to X’s cost for the 30 previous bid in which Contractor X has competed against Contractor Y is given in the Table
Ratio of Y’s bid price to X’s cost | Number of bids |
|---|---|
1.02 | 6 |
1.04 | 12 |
1.06 | 3 |
1.10 | 6 |
1.12 | 3 |
Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 42
Open questionCENAT2 marksNeeds review
The activity details for a small project are given in the Table.
Activity | Duration (days) | Depends on |
|---|---|---|
A | 6 | - |
B | 10 | A |
C | 14 | A |
D | 8 | B |
E | 12 | C |
F | 8 | C |
G | 16 | D, E |
H | 8 | F, G |
K | 2 | B |
L | 5 | G, K |
The total time (in days, in integer) for project completion is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 43
Open questionCENAT2 marksNeeds review
A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table.
Activity | Duration (in weeks) | Depends upon |
|---|---|---|
N | 2 | - |
P | 5 | N |
Q | 3 | N |
R | 4 | P |
S | 5 | Q |
T | 8 | R |
U | 7 | R, S |
V | 2 | U |
W | 3 | U |
X | 5 | T, V |
Y | 1 | W |
Z | 3 | X, Y |
The total float of the activity “V” (in weeks, in integer) is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 43
Open questionCENAT2 marksNeeds review
An equipment has been purchased at an initial cost of ₹16000 and has an estimated salvage value of ₹1000. The equipment has an estimated life of 5 years. The difference between the book values (in ₹, in integer) obtained at the end of 4th year using straight line method and sum of years digit method of depreciation is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 8
Open questionCEMCQ1 markNeeds review
During the process of hydration of cement, due to increase in Dicalcium Silicate (C
S) content in cement clinker, the heat of hydrationYour answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer