Question 13

Open question
CEMCQ1 markNeeds review
Consider the following statements (P) and (Q): (P): Fly ash and ground granulated blast furnace slag can be used as mineral admixtures in concrete. (Q): As per IS 456:2000, the minimum moist curing period becomes higher when a mineral admixture is added to concrete. Identify the CORRECT option from choices given below.
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 16

Open question
CEMCQ1 markNeeds review
Identify the FALSE statement from the following options:
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 23

Open question
CEMSQ1 markNeeds review
In the context of construction materials, which of the following statements is/are CORRECT?
Your answerSelect all correct options. You can choose more than one.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 33

Open question
CENAT1 markNeeds review
If the weights retained on the 2.36 mm, 1.18 mm, 600

m, and 300

m sieves are 30%, 5%, 15%, and 20%, respectively, of the total weight of an aggregate sample, then the fineness modulus of the sample is __________ (rounded off to 2 decimal places).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 42

Open question
CEMSQ2 marksNeeds review
In the context of construction project management, which of the following statements is/are true:
Your answerSelect all correct options. You can choose more than one.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 53

Open question
CENAT2 marksNeeds review
The figure shows a network diagram for a construction project. The activities A, B, C, D, E, and F are represented by arrows and their durations are in the figure.
The total float available for the activity E in day(s) is equal to _____ (round off to the nearest integer).
Diagram for Civil Engineering question 53


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 15

Open question
CE-1MCQ1 markNeeds review
Concrete of characteristic strength 30 MPa is required. If 40 specimens of concrete cubes are to be tested, the minimum number of specimens having at least 30 MPa strength should be
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 16

Open question
CE-1MCQ1 markNeeds review
Consider the statements P and Q.
P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 17

Open question
CE2MCQ1 markNeeds review
Consider the statements P and Q.
P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.
Q: A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.
Which one of the following options is CORRECT?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 19

Open question
CE2MCQ1 markNeeds review
Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200 Budgeted Cost of Work Performed (BCP) = Rs. 150 Actual Cost of Work Performed (ACWP) = Rs. 190
The ‘schedule variance’ for the project is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer