Question 30
Open questionMEMCQ1 markNeeds review
In relation to metal casting defects, match the following
Defect | Description |
|---|---|
P — Dross | I — Shallow blow found on a flat casting surface |
Q — Scab | II — Lighter impurities appear on the top surface of a casting |
R — Scar | III — A rough, thin layer of metal, protruding above the casting surface, on top of a thin layer of sand |
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 38
Open questionMEMCQ2 marksNeeds review
Match the mold elements in the casting process with the most suitable function.
Mold element | Function |
|---|---|
P. Blind riser | I. Cast with internal cavity |
Q. Chill | II. Molten metal reservoir |
R. Skim bob | III. Nucleating agent |
S. Core | IV. Assisting in faster heat removal from melt |
T. Insulating sleeve | V. Removal of impurities |
U. Inoculant | VI. Increasing the solidification time |
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 25
Open questionMEMSQ1 markNeeds review
In a metal casting process to manufacture parts, both patterns and moulds provide shape by dictating where the material should or should not go. Which of the option(s) given correctly describe(s) the mould and the pattern?
Your answerSelect all correct options. You can choose more than one.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 19
Open questionMEMCQ1 markNeeds review
Fluidity of a molten alloy during sand casting depends on its solidification range. The phase diagram of a hypothetical binary alloy of components A and B is shown in the figure with its eutectic composition and temperature. All the lines in this phase diagram, including the solids and liquids lines, are straight lines. If this binary alloy with 15 weight % of B is poured into a mould at a pouring temperature of 800 °C, then the solidification range is

Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 27
Open questionMEMSQ1 markNeeds review
Consider sand cast of a cube of edge length
. A cylindrical riser is placed at the top of the casting. Assume solidification time,
, where
is the volume and
is the total surface area dissipating heat. If the top of the riser is insulated, which of the following radius/radii of riser is/are acceptable?Your answerSelect all correct options. You can choose more than one.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 36
Open questionMENAT2 marksNeeds review
A true centrifugal casting operation needs to be performed horizontally to make copper tube sections with outer diameter of 250 mm and inner diameter of 230 mm. The value of acceleration due to gravity,
m/s
. If a G-factor (ratio of centrifugal force to weight) of 60 is used for casting the tube, the rotational speed required is ______ rpm (round off to the nearest integer).Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 37
Open questionMENAT2 marksNeeds review
A cast product of a particular material has dimensions 75 mm × 125 mm × 20 mm. The total solidification time for the cast product is found to be 2.0 minutes as calculated using Chvorinov’s rule having the index,
= 2. If under the identical casting conditions, the cast product shape is changed to a cylinder having diameter = 50 mm and height = 50 mm, the total solidification time will be ____________ minutes (round off to two decimal places).Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 13
Open questionMEMCQ1 markNeeds review
In a casting process, a vertical channel through which molten metal flows downward from pouring basin to runner for reaching the mold cavity is called
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 50
Open questionMENAT2 marksNeeds review
The figure shows a pouring arrangement for casting of a metal block.

Frictional losses are negligible. The acceleration due to gravity is 9.81 m/s². The time (in s, round off to two decimal places) to fill up the mold cavity (of size 40 cm × 30 cm × 15 cm) is _____
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 13
Open questionMEMCQ1 markNeeds review
During solidification of a pure molten metal, the grains in the casting near the mould wall are
Your answerChoose one option.
Log in to check the answer