In a mine bench, the shovel loading time follows exponential distribution with a mean loading time of 5 min per dumper. The arrival rate of dumpers that are identical in capacity, follows Poisson distribution with a mean arrival rate of 8 per hour. The probability that the shovel remains idle is __________ (round off to 2 decimal places).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 31

Open question
MNMCQ2 marksNeeds review
A linear programming problem is stated below.
Maximize

subject to,



The objective function has
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 34

Open question
MNNAT2 marksNeeds review
A surface mine production system along with the reliability of the individual components is shown below. The system reliability is ________ (round off to 3 decimal places).
Diagram for Mining Engineering question 34


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 53

Open question
MNNAT2 marksNeeds review
An assignment problem is given below with the cost of assignment as shown.
Group
T1
T2
T3
T4
G1
6
10
5
4
G2
4
100
6
4
G3
6
9
6
2
G4
3
7
6
4
If only one task can be assigned to one group, the minimum cost of assignment is ________.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 10

Open question
MNMCQ1 markNeeds review
In project planning, the activity durations are calculated by PERT and CPM techniques assuming
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 19

Open question
MNNAT1 markNeeds review
If the time to failure of a machine component is exponentially distributed, the reliability of the same at Mean Time To Failure (MTTF), (rounded off to three decimal places), is __________.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 37

Open question
MNNAT2 marksNeeds review
In the linear programming problem,
Maximize

Subject to:









, and

The value of Z is

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 47

Open question
MNNAT2 marksNeeds review
For a mining company the unit transportation cost from a mine to a washery, and supply and demand are shown below:


Washery


Supply
Mine

A
B
C
D
M1

30
0
40
20
500
M2

24
16
22
40
700
M3

0
32
28
36
800
Demand

300
400
600
700

The total cost of transportation using the Vogel’s approximation method is

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 15

Open question
MNMCQ1 markNeeds review
The inventory pattern shown does NOT represent the following.
Diagram for Mining Engineering question 15

Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 16

Open question
MNMCQ1 markNeeds review
The figure depicts a transportation problem along with the solution. The correct statement is
Diagram for Mining Engineering question 16