Question 50

Open question
MNNAT2 marksNeeds review
A shovel costing (

) ₹ 20 crores has a salvage value (

) of ₹ 2 crores with a useful life (

) of 10 years. The annual depreciation is evaluated using declining balance method as given by

The depreciated cost of the shovel, in crores, in its 2

year is ₹ _____________. (rounded off to two decimal place)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
MNNAT2 marksNeeds review
An economic block model along with extraction sequence is shown. The numbers given at the centre of the block represent the year of extraction, and that at the corners represent the block economic value in ₹ (lakhs). If the discount rate is 10%, the net present value (NPV), in lakhs, is ₹ __________. (rounded off to two decimal place)
Diagram for Mining Engineering question 51


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 35

Open question
MNNAT1 markNeeds review
The relevant information on metal extraction from a copper mine are given below
Selling price of copper (Rs./kg) = 900
Mining cost (Rs./tonne of ore) = 500
Processing cost (Rs./tonne of ore) = 2000
Overall recovery of copper metal (%) = 70
Ignoring all other costs, the breakeven cutof grade of copper, in %, is _____ (rounded off to 2 decimal places)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 60

Open question
MNNAT2 marksNeeds review
The information of a mining project for a life of three years is given below:

Year 0
Year 1
Year 2
Year 3
Revenue (Crore Rupees)

200
300
400
Capital cost (Crore Rupees)
300



Operating cost (Crore Rupees)

30
40
35
Applicable tax rate = 30 %
Discount rate = 10 %
If straight line depreciation with zero salvage value is applicable, the NPV, in Crore Rupees, is ____ (rounded off to 2 decimal places)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 24

Open question
MNMCQ1 markNeeds review
The function of District Mineral Foundation established by state governments in India, is to
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 58

Open question
MNNAT2 marksNeeds review
In an open pit mine, the mineral inventory, prices, costs and capacities are given.
Mineral inventory
Grade interval
Tonnage (in million tonne)
0 < Cu% ≤ 0.3
0
0.3 < Cu% ≤ 0.4
5
0.4 < Cu% ≤ 0.5
5
0.5 < Cu% ≤ 0.6
5
0.6 < Cu% ≤ 0.7
5
0.7 < Cu% ≤ 0.8
5
0.8 < Cu%
0
Concentrating cost : INR 3,200/tonne of ore milled Smelting & refinery cost : INR 10,000/tonne of copper metal Selling price : INR 6,50,000/tonne of copper metal Overall recovery : 100% Maximum production capacity : 5 million tonne/annum
The mine is operating at 5 million tonne in a year. Considering mine capacity being the only constraint, Lane’s algorithm (based on profit maximization) is used for determining mill cut-off grade. The total amount of copper produced in million tonne, in the life of the pit, is _____. (round off up to 2 decimals)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 60

Open question
MNNAT2 marksNeeds review
The real rate of return from a mining project is 14%. If the inflation rate over the entire life of the mine is 5.5 %, then the nominal rate of return in %, is _____. (round off up to 2 decimals)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 28

Open question
MNNAT1 markNeeds review
The average ore grade of a copper deposit is 0.9%. The recovery of the metal after processing, smelting and refining is 85%. If the selling price of refined copper is Rs 640/kg, the sale value in Rs. from mining one tonne of ore is_____. [rounded off to 1 decimal place]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 56

Open question
MNNAT2 marksNeeds review
A thermal power station receives coal of calorific value 4000 kcal/kg and uses 700 tonnes of coal every day. Assuming 860 kcal is the heat equivalent of 1.0 kWh, for a thermal efficiency of 40% and electrical efficiency of 85% the power generation per day in MWh is _____.
[rounded off to 1 decimal place]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 61

Open question
MNNAT2 marksNeeds review
A mining company makes an initial investment of Rs 200 crore on a project.
The following data are available:
Production life : 3 years Year wise production after gestation period (Mtonne) : 1.0, 2.0, and 1.0 Stripping ratio : 1.5 m³/tonne Selling price of ore : Rs. 200 per tonne Ore mining cost : Rs. 500 per tonne Waste mining cost : Rs. 500 per m³ Discount rate : 10%
By ignoring any other cash-flows, if the NPV of the project becomes Rs. 5.367 crore, the gestation period of the project, in years is _____.
[rounded off to the nearest integer]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer