Question 33
Open questionPINAT1 markNeeds review
If the interarrival time is exponential and 8 customers per hour arrive in a bank, then the probability of no arrival of customer during a period of 15 minutes is____________. [round off to two decimal places]
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 62
Open questionPINAT2 marksNeeds review
A vaccine has to be distributed from two warehouses to three hospitals. The supplies at warehouses W₁ and W₂ are 200 and 150, respectively. The demands at hospitals H₁, H₂, and H₃ are 100, 150 and 125, respectively. The transportation cost (in ₹) per vaccine is as follows:
| | H₁ | H₂ | H₃ |
| W₁ | 5 | 7 | 3 |
| W₂ | 4 | 6 | 7 |
The initial basic feasible solution using the Northwest-corner method provides the total transportation cost (in ₹) as____________. [round off to nearest integer]
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 63
Open questionPINAT2 marksNeeds review
Consider the linear programming problem:
Maximize
,subject to
(C₁)
(C₂)
(C₃)
The optimal solution is given as
,
and
. The dual variables of constraints C₁, C₂ and C₃ are
,
and
, respectively. The optimal values of dual variables are
,
and
. The value of parameter P in the objective function is____________. [round off to one decimal place]Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 32
Open questionPIMCQ2 marksNeeds review
A company manufactures two products P and Q with unit profit of 4 and 5, respectively. The production requires manpower and two kinds of raw materials R1 and R2. The following table summarizes the requirement and availability of resources.
Resource | Resource usage per unit of production P | Q | Amount of resource available |
|---|---|---|---|
manpower | 1 | 1 | 10 |
R1 | 1 | 2 | 18 |
R2 | 2 | 1 | 18 |
The maximum profit the company can make is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 21
Open questionPIMCQ1 markNeeds review
The Bellman’s principle of optimality is related to
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 33
Open questionPIMCQ2 marksNeeds review
A company manufactures products P and Q in quantities
and
, respectively, using two resources. The following Linear Programming Problem (LPP) is formulated to maximize the profit Z.Maximize
subject to
(for Resource 1)
(for Resource 2)
and
.The shadow price for Resource 2 is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 25
Open questionPINAT1 markNeeds review
A warehouse has 1 loading dock and 3 persons for loading operations. The arrival rate of trucks follows Poisson distribution with a mean of 4 trucks/hour. The average loading time (by three persons together) per truck is exponentially distributed with a mean of 10 minutes. The charge of the trucks per hour and loading charges per person per hour are Rs.20 and Rs.6, respectively. The total cost (in Rs./hour) is _____
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 33
Open questionPIMCQ2 marksNeeds review
An LPP is defined as
Minimize
subject to,
The objective function of the dual of this LPP is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 31
Open questionPIMCQ2 marksNeeds review
In a service centre, cars arrive according to Poisson distribution with a mean of 2 cars per hour. The time for serving a car is exponential with a mean of 15 minutes. The expected waiting time (in minute) in the queue is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 44
Open questionPINAT2 marksNeeds review
A company has two manufacturing plants (C
and C
) and two distribution centres (D
and D
). The capacities of C
and C
are 100 and 200 units, respectively. The demand for D
and D
are 190 and 110 units, respectively. The costs per unit (in Rs.) of transportation at different routes are as per the following matrix: | | D
| D
| C
| 22 | 21 | C
| 20 | 27 | The minimum total cost (in Rs.) of transportation is _____Log in to check the answer