Question 46

Open question
ARNAT2 marksNeeds review
A construction project consists of four activities. The quantity of work, manpower requirement, and the productivity of the activities are listed in the table below. The interrelationship between the activities are also mentioned in the table. The construction project will start on January 29. Assume no holidays for the entire duration of the project. The project will finish in February _____ [mention date in number].
Activity
Quantity (cu.m)
Manpower (persons)
Productivity (cu.m/ man-day)
Immediate Successor Activity
A
96
8
3
C
B
252
7
4
C & D
C
275
5
5
Nil
D
126
6
3
Nil

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 47

Open question
ARNAT2 marksNeeds review
For a privately developed group housing project, the ratio of total number of dwelling units of HIG: MIG: LIG is 3:2:1. The proposed average size of HIG, MIG and LIG units in sq.m are 100, 60 and 30 respectively. The ratio of the total built up area between (MIG + LIG) to HIG will be 1: _____ [in integer].

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 48

Open question
ARNAT2 marksNeeds review
The surface development of a three dimensional object is shown in the figure below. The dotted lines indicate the folds. The dimensions given in the figure are in centimeter. The volume of the three-dimensional object (in cu.cm) is__________ [rounded off to one decimal place].
Diagram for Architecture and Planning question 48


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer