Question 64
Open questionCENAT2 marksNeeds review
The wastewater inflow to an activated sludge plant is 0.5 m³/s, and the plant is to be operated with a food to microorganism ratio of 0.2 mg/mg-d. The concentration of influent biodegradable organic matter to the plant (after primary settling) is 150 mg/L, and the mixed liquor volatile suspended solids concentration to be maintained in the plant is 200 mg/L. Assuming that complete removal of biodegradable organic matter in the tank, the volume of aeration tank (in m³, in integer) required for the plant is ________________.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 65
Open questionCENAT2 marksNeeds review
Trigonometric levelling was carried out from two stations P and Q to find the reduced level (R. L.) of the top of hillock, as shown in the table. The distance between Stations P and Q is 55 m. Assume Stations P and Q, and the hillock are in the same vertical plane. The R. L. of the top of the hillock (in m) is ________________________ (round off to three decimal places).
Station | Vertical angle of the top of hillock | Staff reading on benchmark | R. L. of benchmark |
|---|---|---|---|
P | 18°45′ | 2.340 m | 100.000 m |
Q | 12°45′ | 1.660 m | |
Log in to check the answer