Question 16

Open question
CE-1MCQ1 markNeeds review
Consider the statements P and Q.
P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 17

Open question
CE-1MCQ1 markNeeds review
The following figure shows the arrangement of formwork for cast a cantilever RC beam.
Diagram for Civil Engineering question 17

The correct sequence of removing the Shores/Props is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 18

Open question
CE-1MCQ1 markNeeds review
A 2 m wide strip footing is found at a depth of 1.5 m below the ground level in a homogenous pure clay bed. The clay bed has unit cohesion of 40 kPa. Due to seasonal fluctuations of water table from peak summer to peak monsoon period, the net ultimate bearing capacity of the footing, as per Terzaghi’s theory, will
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer