Question 58

Open question
CE2NAT2 marksNeeds review
A 2 m × 1.5 m tank of 6 m height is provided with a 100 mm diameter orifice at the center of its base. The orifice is plugged and the tank is filled up to 5 m height. Consider the average value of discharge coefficient as 0.6 and acceleration due to gravity (

) as 10 m/s

. After unplugging the orifice, the time (in seconds) taken for the water level to drop from 5 m to 3.5 m under free discharge condition is __________ (rounded off to 2 decimal places).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 59

Open question
CE2NAT2 marksNeeds review
A rectangular channel is 4.0 m wide and carries a discharge of 2.0 m

/s with a depth of 0.4 m. The channel transitions to a maximum width contraction at a downstream location, without influencing the upstream flow conditions. The width (in meters) at the maximum contraction is ______________ (rounded off to 2 decimal places).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 60

Open question
CE2NAT2 marksNeeds review
A circular settling tank is to be designed for primary treatment of sewage at a flow rate of 10 million liters/day. Assume a detention period of 2.0 hours and surface loading rate of 4000 liters/m

/day. The height (in meters) of the water column in the tank is ______________ (rounded off to 2 decimal places).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer