Complete GATE CE 2024 Paper 2 overview, original pages and practice · Timed previous-paper practice

Questions 19–21 of 65. Imported answers require review unless explicitly marked reviewed.

Paper practice 65 questionsPage 7 of 22

Question 19

Open question
CE2MCQ1 markNeeds review
Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200 Budgeted Cost of Work Performed (BCP) = Rs. 150 Actual Cost of Work Performed (ACWP) = Rs. 190
The ‘schedule variance’ for the project is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 20

Open question
CE2MCQ1 markNeeds review
A simply supported, uniformly loaded, two-way slab panel is torsionally unrestrained. The effective span lengths along the short span (x) and long span (y) directions of the panel are

and

, respectively. The design moments for the reinforcements along the x and y directions are

and

, respectively. By using Rankine-Grashof method, the ratio

is proportional to
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 21

Open question
CE2MCQ1 markNeeds review
The structural design method that DOES NOT take into account the safety factors on the design loads is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer