Question 19
Open questionCE2MCQ1 markNeeds review
Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190
The ‘schedule variance’ for the project is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 20
Open questionCE2MCQ1 markNeeds review
A simply supported, uniformly loaded, two-way slab panel is torsionally unrestrained. The effective span lengths along the short span (x) and long span (y) directions of the panel are
and
, respectively. The design moments for the reinforcements along the x and y directions are
and
, respectively. By using Rankine-Grashof method, the ratio
is proportional toYour answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 21
Open questionCE2MCQ1 markNeeds review
The structural design method that DOES NOT take into account the safety factors on the design loads is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer