Question 49
Open questionME-1MCQ2 marksNeeds review
Circular arc on a part profile is being machined on a vertical CNC milling machine. CNC part program using metric units with absolute dimensions is listed below:
N60 G01 X 30 Y 55 Z -5 F50
N70 G02 X 50 Y 35 R 20
N80 G01 Z 5
The coordinates of the centre of the circular arc are:
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 50
Open questionME-1MCQ2 marksNeeds review
Assume that the surface roughness profile is triangular as shown schematically in the figure. If the peak to valley height is 20 μm, the central line average surface roughness
(in μm) is 
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 51
Open questionME-1NAT2 marksNeeds review
Two models, P and Q, of a product earn profits of Rs. 100 and Rs. 80 per piece, respectively. Production times for P and Q are 5 hours and 3 hours, respectively, while the total production time available is 150 hours. For a total batch size of 40, to maximize profit, the number of units of P to be produced is ________
Log in to check the answer