Complete GATE ME 2021 Paper 1 overview, original pages and practice · Timed previous-paper practice

Questions 43–45 of 65. Imported answers require review unless explicitly marked reviewed.

Paper practice 65 questionsPage 15 of 22

Question 33

Open question
MEMCQ2 marksNeeds review
Customers arrive at a shop according to the Poisson distribution with a mean of 10 customers/hour. The manager notes that no customer arrives for the first 3 minutes after the shop opens. The probability that a customer arrives within the next 3 minutes is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 34

Open question
MEMCQ2 marksNeeds review
Let

be a continuous function defined on

. The point

at which the tangent of

becomes parallel to the straight line joining

and

is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 35

Open question
MENAT2 marksNeeds review
Activities A, B, C and D for the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other.
Activity
A
B
C
D
Mean (days)
6
11
8
15
Variance (days

)
4
9
4
9
The probability that the project will be completed within 40 days is ______ (round off to two decimal places).
(Note: Probability is a number between 0 and 1).