Question 39
Open questionMNNAT2 marksNeeds review
In a sublevel stope, 20 m high excavation is made with ring drilling in a 6 m wide orebody. In an effective shift time of 6 hrs, three rings are blasted resulting in 9 m extraction length. LHDs of 5.0
bucket capacity and cycle time of 5 minutes are used for ore transportation. The number of LHDs required for this operation is _________________.Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 40
Open questionMNNAT2 marksNeeds review
A coal seam lying at a depth of 200 m is developed by bord and pillar method. Pillars are 30 m centre to centre with a gallery width of 4 m. Unit weight of the overlying strata is 28
. If the pillar strength is 9.32 MPa, the factor of safety of pillar is ___________.Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 41
Open questionMNNAT2 marksNeeds review
Following information about a longwall retreating panel is given.
Panel length = 1800 m
Face length = 150 m
Depth of web = 0.6 m
Shearer travels at a speed of 1.5 m/min along the face.
Each cutting cycle requires a non-operational time of 2 h 20 min. The panel is fully extractable. The number of working days required to extract the panel is ______________.