Question 36
Open questionMNNAT2 marksNeeds review
A double ended ranging drum shearer operates in a longwall retreating panel. The following data are provided:
Face length: 200 m
Web depth: 0.6 m
Cutting height: 2.5 m
Density of coal: 1.4 tonne/m
Average cutting speed: 1.5 m/min
Average flitting speed: 4.0 m/min
Number of shifts/day: 3Method of cutting is unidirectional and each shift requires a non-operational time of 2.0 hours. The production per day in tonne (rounded off to one decimal place) is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 37
Open questionMNNAT2 marksNeeds review
In the linear programming problem,
Maximize
Subject to:
, and
The value of Z is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 38
Open questionMNNAT2 marksNeeds review
A shovel operates 300 days in a year, 2 shifts in a day, and 4 hours in a shift to achieve the target production of 30 Million tonne per annum. The following parameters relate to the loading operation:
Bucket capacity of shovel: 15 m
Shovel cycle time: 44 s
Bucket fill factor: 0.85
Bulk density of the muck: 3.00 tonne/m
The minimum number of shovels required to achieve the production is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer