Question 10
Open questionGAMCQ2 marksNeeds review
Three villages P, Q, and R are located in such a way that the distance PQ = 13 km, QR = 14 km, and RP = 15 km, as shown in the figure. A straight road joins Q and R. It is proposed to connect P to this road QR by constructing another road. What is the minimum possible length (in km) of this connecting road?
Note: The figure shown is representative.

Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 11
Open questionMNMCQ1 markNeeds review
A non-transit theodolite does NOT have
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 12
Open questionMNMCQ1 markNeeds review
A steeply dipping metalliferous ore body is non-susceptible to spontaneous heating. The blasted ore is used as the platform to work in a stope. Appropriate mining method for this orebody is
Your answerChoose one option.
Log in to check the answer