The borehole data for resource estimation for an iron ore deposit are shown. The average grade of the deposit, in %, is ____________. (rounded off to two decimal places)
Plan view: A1 = 0.02 km², A2 = 0.03 km², A3 = 0.04 km². Borehole sections: D1 has 6 m at 63% and 6 m at 66%; D2 has 6 m at 60% and 4 m at 64%; D3 has 8 m at 64% and 7 m at 62%. Index: D1 to D3: Exploratory Borehole ID; A1 to A3: Corresponding Polygonal Area.
Diagram for Mining Engineering question 46


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 47

Open question
MNNAT2 marksNeeds review
A mine workshop needs to assign 4 jobs to 4 service engineers. The cost for performing a job by an individual service engineer is given. A typical job can be assigned to only one service engineer. If the service engineer S1 cannot perform the job J3, and S3 cannot perform the job J4, the optimal cost for completion of jobs is ____________. (answer in integer)
Service Engineer
J1
J2
J3
J4
S1
50
50
---
20
S2
70
40
20
70
S3
90
30
50
---
S4
70
20
60
30

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 48

Open question
MNNAT2 marksNeeds review
Using linear regression (least squares), the best-fit line for the given dataset is y = 2.2x + 2.3. Given the residual sum of squares is 25.8, the coefficient of determination (

), is _____________. (rounded off to two decimal places)
x
2
3
4
5
y
8
9
7
16