Question 61

MNNAT2 marksNeeds review
A bord and pillar panel has 24 developed pillars of size 40 m × 40 m (centre to centre) under extraction. The following information is given:
Gallery width = 4 m Extraction height = 3 m Extraction ratio during depillaring = 80% Specific gravity of coal = 1.4 Incubation period = 6 months Average working days per month = 25
In order to extract the panel within the incubation period, the minimum rate of production, in tonne per day, is ______________. (rounded off to one decimal place)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2026MN

GATE MN 2026 · Paper 1

Mining Engineering · Original paper archive

Section
Mining Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mining engineering

GATE MN previous year questions

mining

GATE MN previous year questions

mineral processing

GATE MN previous year questions

underground hazards

GATE MN previous year questions

mining methods

GATE MN previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.