A double ended range drum (DERD) shearer uni-directionally cuts coal in a longwall panel having the following details
Shearer drum diameter = 1.4 m
Panel dimension = 1200 m × 200 m × 2.4 m
Web depth = 0.6 m
Average cutting speed = 5 m/minute
Average retreating speed = 10 m/minute
Average operational delay between cuts is 2 hour. There are two production shifts, each of 8 hour duration. The number of days required for complete extraction of the panel is ____ (in integer)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2025MN

GATE MN 2025 · Paper 1

Mining Engineering · Original paper archive

Section
Mining Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mining engineering

GATE MN previous year questions

mining

GATE MN previous year questions

mineral processing

GATE MN previous year questions

mining methods

GATE MN previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.