A machine shop has received four jobs A, B, C and D for processing on a single CNC machine. All jobs are available for processing on the first day of the production schedule calendar, and processing times and due dates as applicable on the first day are given below. Using earliest due date rule, the average tardiness (in days) is ________. [in integer]
Job | Processing time (in days) | Due date (day) |
|---|---|---|
A | 8 | 14 |
B | 5 | 10 |
C | 7 | 12 |
D | 9 | 19 |
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2021PI
GATE PI 2021 · Paper 1
Production and Industrial Engineering · Original paper archive
- Section
- Production and Industrial Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
production engineering
GATE PI previous year questions
industrial engineering
GATE PI previous year questions
manufacturing
GATE PI previous year questions
production control
GATE PI previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.