Question 39

PINAT2 marksNeeds review
A machine shop has received four jobs A, B, C and D for processing on a single CNC machine. All jobs are available for processing on the first day of the production schedule calendar, and processing times and due dates as applicable on the first day are given below. Using earliest due date rule, the average tardiness (in days) is ________. [in integer]
Job
Processing time (in days)
Due date (day)
A
8
14
B
5
10
C
7
12
D
9
19

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2021PI

GATE PI 2021 · Paper 1

Production and Industrial Engineering · Original paper archive

Section
Production and Industrial Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

production engineering

GATE PI previous year questions

industrial engineering

GATE PI previous year questions

manufacturing

GATE PI previous year questions

production control

GATE PI previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.