Question 59: Operations Research
Give it a try, then reveal the answer to check your work.
Question 59
MENAT2 marksNeeds review
A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is __________ weeks (in integer).
Activity | Optimistic time | Most likely time | Pessimistic time | Immediate predecessor(s) |
|---|---|---|---|---|
A | 4 | 5 | 6 | None |
B | 1 | 3 | 5 | A |
C | 1 | 2 | 3 | A |
D | 2 | 4 | 6 | C |
E | 3 | 4 | 5 | B, D |
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2022ME
GATE ME 2022 · Paper 2
Mechanical Engineering · Original paper archive
- Section
- Mechanical Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mechanical engineering
GATE ME previous year questions
mechanics
GATE ME previous year questions
manufacturing
GATE ME previous year questions
operations research
GATE ME previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.