A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is __________ weeks (in integer).
Activity
Optimistic time
Most likely time
Pessimistic time
Immediate predecessor(s)
A
4
5
6
None
B
1
3
5
A
C
1
2
3
A
D
2
4
6
C
E
3
4
5
B, D

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2022ME

GATE ME 2022 · Paper 2

Mechanical Engineering · Original paper archive

Section
Mechanical Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mechanical engineering

GATE ME previous year questions

mechanics

GATE ME previous year questions

manufacturing

GATE ME previous year questions

operations research

GATE ME previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.