Question 38

MENAT2 marksNeeds review
A spot welding operation performed on two pieces of steel yielded a nugget with a diameter of 5 mm and a thickness of 1 mm. The welding time was 0.1 s. The melting energy for the steel is 20 J/mm³. Assuming the heat conversion efficiency is 10%, the power required for performing the spot welding operation is ____________ kW (round off to two decimal places).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2021ME

GATE ME 2021 · Paper 2

Mechanical Engineering · Original paper archive

Section
Mechanical Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mechanical engineering

GATE ME previous year questions

mechanics

GATE ME previous year questions

manufacturing

GATE ME previous year questions

Casting, Forming and Joining Processes

GATE ME previous year questions

welding

GATE ME previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.