GATE CE · 2019 · CE
Question 40: Water and Waste Water Quality and Treatment
Give it a try, then reveal the answer to check your work.
Question 40
CENAT2 marksNeeds review
A water treatment plant treats 6000
of water per day. As a part of the treatment process, discrete particles are required to be settled in a clarifier. A column test indicates that an overflow rate of 1.5
per hour would produce the desired removal of particles through settling in the clarifier having a depth of 3.0
. The volume of the required clarifier, (in
, round off to 1 decimal place) would be __________Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2019CE
GATE CE 2019 · Paper 2
Civil Engineering · Original paper archive
- Section
- Civil Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
civil engineering
GATE CE previous year questions
infrastructure
GATE CE previous year questions
structural engineering
GATE CE previous year questions
water and wastewater treatment
GATE CE previous year questions
Water and Waste Water Quality and Treatment
GATE CE previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.