Question 43

MNNAT2 marksNeeds review
An SDL of 1.0 tonne capacity operates with a cycle time of 6 minutes. The dimension of the face is 4 m x 3 m. Five blasts are conducted per shift with an average pull of 1.2 m. If the density of blasted coal is 0.8 tonne/m

, the time required by the SDL in the shift to lift all the prepared coal in hours is ____________________.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2018MN

GATE MN 2018 · Paper 1

Mining Engineering · Original paper archive

Section
Mining Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mining engineering

GATE MN previous year questions

mining

GATE MN previous year questions

mineral processing

GATE MN previous year questions

mining machinery

GATE MN previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.