Question 26

PIMCQ2 marksNeeds review
For a given process control chart, there are four rules for determining out-of-control state of the process which are being used simultaneously. The probability of Type-I error for the four rules are 0.005, 0.02, 0.03, and 0.05. Assuming independence of the rules, the probability of overall Type-I error when all the four rules are used simultaneously is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2021PI

GATE PI 2021 · Paper 1

Production and Industrial Engineering · Original paper archive

Section
Production and Industrial Engineering
Question type
Multiple choice (MCQ)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

production engineering

GATE PI previous year questions

industrial engineering

GATE PI previous year questions

manufacturing

GATE PI previous year questions

quality management

GATE PI previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.