Question 65: Mine Development
Give it a try, then reveal the answer to check your work.
Question 65
MNNAT2 marksNeeds review
In a development coal face, 12 holes are drilled and charged with explosive. Holes are initiated with electric delay detonators connected in series. The length of a detonator lead wire is 1.5 m. The length of the blasting cable is 120 m.
Data are as given:
Resistance of each detonator: 1.48 Ω
Resistance of lead wire: 0.04 Ω/m
Resistance of one wire of the blasting cable: 0.009 Ω/m
The total resistance of the circuit in Ω, is _____. (round off up to 2 decimals)
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2024MN
GATE MN 2024 · Paper 1
Mining Engineering · Original paper archive
- Section
- Mining Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mining engineering
GATE MN previous year questions
mining
GATE MN previous year questions
mineral processing
GATE MN previous year questions
mine development
GATE MN previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.