Question 49

PIMCQ2 marksNeeds review
In a machine shop, four jobs need to be assigned to four different machines. Each of the jobs is to be assigned to one machine only at a time. The time taken to complete the job in different machines is given in the Table.
Jobs / Machines
M₁
M₂
M₃
M₄
J₁
15
13
14
17
J₂
11
12
15
13
J₃
13
12
10
11
J₄
15
17
14
16
In order to ensure that the total time required to complete all the jobs is minimum, the optimal assignment of the job is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2017PI

GATE PI 2017 · Paper 1

Production and Industrial Engineering · Original paper archive

Section
Production and Industrial Engineering
Question type
Multiple choice (MCQ)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

production engineering

GATE PI previous year questions

industrial engineering

GATE PI previous year questions

manufacturing

GATE PI previous year questions

operation research

GATE PI previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.