Question 43: Services and Infrastructure
Give it a try, then reveal the answer to check your work.
Question 43
ARNAT2 marksNeeds review
In a residential complex, the central play area is to be converted as a detention pond for storm water management. For a 24 hour rainfall event of 100 mm, 100% storm water of central play area and 70% storm water run-off from rest of the complex is to be held at the detention pond. Area distribution in the residential complex is given in the table.
Type | Area (m²) | Run-off coefficient |
|---|---|---|
Apartment Blocks | 1250 | 0.80 |
Central Play Area | 150 | 0.60 |
Other Permeable Areas | 200 | 0.70 |
Other Impermeable Areas | 400 | 0.90 |
The required depth of the detention pond (in mm) is ________
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2020AR
GATE AR 2020 · Paper 1
Architecture and Planning · Original paper archive
- Section
- Architecture and Planning
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
architecture
GATE AR previous year questions
urban planning
GATE AR previous year questions
built environment
GATE AR previous year questions
services infrastructure
GATE AR previous year questions
Services and Infrastructure
GATE AR previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.