Question 53: Mining Machinery
Give it a try, then reveal the answer to check your work.
Question 53
MNNAT2 marksNeeds review
In a surface mine bench, overburden is removed by the shovel-dumper combination. For the dumper:
Time required at the loading station: 3.0 min
Time required at the unloading station: 1.0 min
Distance between loading and unloading stations: 4.5 km
Average speed during loaded travel: 12.0 km/hr
Average speed during empty travel: 18.0 km/hr
Minimum number of dumpers required to avoid idle time of the shovel, is ______. (in integer)
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2022MN
GATE MN 2022 · Paper 1
Mining Engineering · Original paper archive
- Section
- Mining Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mining engineering
GATE MN previous year questions
mining
GATE MN previous year questions
mineral processing
GATE MN previous year questions
mining machinery
GATE MN previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.