Question 53: Metal cast
Give it a try, then reveal the answer to check your work.
Question 53
MTNAT2 marksNeeds review
In a top gated mold, liquid metal enters the mold cavity as a freely falling stream under gravity from a height of 0.5 m. Ignore the fluid friction due to viscosity and the drag due to changes in the direction of flow. If the volume of the mold cavity is 10 m
, then the time required to fill the mold is ______ s (round off to nearest integer).Given:
Acceleration due to gravity is 9.8 m s
.Cross-sectional area of gate is 0.2 m
.Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2020MT
GATE MT 2020 · Paper 1
Metallurgical Engineering · Original paper archive
- Section
- Metallurgical Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
metallurgy
GATE MT previous year questions
materials science
GATE MT previous year questions
materials engineering
GATE MT previous year questions
metal cast
GATE MT previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.