GATE ME · 2020 · GA
Question 8: Quantitative Aptitude
Give it a try, then reveal the answer to check your work.
Question 8
GAMCQ2 marksNeeds review
It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2020GA
GATE ME 2020 · Paper 2
Mechanical Engineering · Original paper archive
- Section
- General Aptitude
- Question type
- Multiple choice (MCQ)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mechanical engineering
GATE ME previous year questions
mechanics
GATE ME previous year questions
manufacturing
GATE ME previous year questions
quantitative aptitude
GATE ME previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.