GATE XH-C5 · 2024 · GA
Question 8: Quantitative Aptitude
Give it a try, then reveal the answer to check your work.
Question 8
GAMCQ2 marksNeeds review
The chart given below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).

The Capacity Factor of a power generation technology is:
Capacity Factor = Electricity Generation (MWh) / (Installed Capacity (MW) × 1000 (h))
Which one of the given technologies has the highest Capacity Factor?
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2024GA
GATE XH-C5 2024 · Paper 1
Humanities and Social Sciences (Psychology) · Original paper archive
- Section
- General Aptitude
- Question type
- Multiple choice (MCQ)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
psychology
GATE XH-C5 previous year questions
behavioral science
GATE XH-C5 previous year questions
social science
GATE XH-C5 previous year questions
quantitative aptitude
GATE XH-C5 previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.