GATE CE · 2019 · CE
Question 22: Geomatics Engineering
Give it a try, then reveal the answer to check your work.
Question 22
CENAT1 markNeeds review
The data from a closed traverse survey PQRS (run in the clockwise direction) are given in the table
Line | Included angle (in degrees) |
|---|---|
PQ | 88 |
QR | 92 |
RS | 94 |
SP | 89 |
The closing error for the traverse PQRS (in degrees) is ______
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2019CE
GATE CE 2019 · Paper 2
Civil Engineering · Original paper archive
- Section
- Civil Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 1 mark
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
civil engineering
GATE CE previous year questions
infrastructure
GATE CE previous year questions
structural engineering
GATE CE previous year questions
geomatics engineering
GATE CE previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.