The old concert hall was demolished because of fears that the foundation would be affected by the construction of the new metro line in the area. Modern technology for underground metro construction tried to mitigate the impact of pressurized air pockets created by the excavation of large amounts of soil. But even with these safeguards, it was feared that the soil below the concert hall would not be stable.
From this, one can infer that
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2017GA

GATE CH 2017 · Paper 1

Chemical Engineering · Original paper archive

Section
General Aptitude
Question type
Multiple choice (MCQ)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

chemical engineering

GATE CH previous year questions

process engineering

GATE CH previous year questions

chemical processes

GATE CH previous year questions

verbal aptitude

GATE CH previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.