Civil Engineering
GATE CE Construction Materials and Management PYQs
Build your understanding with focused practice from past exam papers.
Questions 41–46 of 46. Imported answers require independent review unless marked reviewed.
Question 3
Open questionCE-2MCQ1 markNeeds review
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 15
Open questionCE-2MCQ1 markNeeds review
Let the characteristic strength be defined as that value, below which not more than 5% of the results are expected to fall. Assuming a standard deviation of 4 MPa, the target mean strength (in MPa) to be considered in the mix design of a M25 concrete would be
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 18
Open questionCE-2NAT1 markNeeds review
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate
for the 95% confidence level. The maximum time required (in days) for the completion of the project would be _________.Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 30
Open questionCE-2MCQ2 marksNeeds review
Group I gives a list of test methods and test apparatus for evaluating some of the properties of Ordinary Portland Cement (OPC) and concrete. Group II gives the list of these properties.
Group I
P. Le Chatelier test
Q. Vee-Bee test
R. Blaine air permeability test
S. The Vicat apparatus
Group II
Soundness of OPC
Consistency and setting time of OPC
Consistency or workability of concrete
Fineness of OPC
The correct match of the items in Group I with the items in Group II is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 33
Open questionCE-2MCQ2 marksNeeds review
Consider the following statements:
P. Walls of one brick thick are measured in square meters.
Q. Walls of one brick thick are measured in cubic meters.
R. No deduction in the brickwork quantity is made for openings in walls up to 0.1 m² area.
S. For the measurement of excavation from the borrow pit in a fairly uniform ground, deadmen are left at suitable intervals.
For the above statements, the correct option is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 45
Open questionCENAT2 marksNeeds review
The activity details of a project are given below:
Activity | Depends on | Duration (in days) |
|---|---|---|
P | -- | 6 |
Q | P | 15 |
R | Q, T | 12 |
S | R | 16 |
T | P | 10 |
U | Q, T | 14 |
V | U | 16 |
The estimated minimum time (in days) for the completion of the project will be
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer