Questions 41–46 of 46. Imported answers require independent review unless marked reviewed.

Topic practice 46 questionsPage 5 of 5

Question 3

Open question
CE-2MCQ1 markNeeds review
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 15

Open question
CE-2MCQ1 markNeeds review
Let the characteristic strength be defined as that value, below which not more than 5% of the results are expected to fall. Assuming a standard deviation of 4 MPa, the target mean strength (in MPa) to be considered in the mix design of a M25 concrete would be
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 18

Open question
CE-2NAT1 markNeeds review
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate

for the 95% confidence level. The maximum time required (in days) for the completion of the project would be _________.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 30

Open question
CE-2MCQ2 marksNeeds review
Group I gives a list of test methods and test apparatus for evaluating some of the properties of Ordinary Portland Cement (OPC) and concrete. Group II gives the list of these properties.
Group I P. Le Chatelier test Q. Vee-Bee test R. Blaine air permeability test S. The Vicat apparatus
Group II
Soundness of OPC
Consistency and setting time of OPC
Consistency or workability of concrete
Fineness of OPC
The correct match of the items in Group I with the items in Group II is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 33

Open question
CE-2MCQ2 marksNeeds review
Consider the following statements: P. Walls of one brick thick are measured in square meters. Q. Walls of one brick thick are measured in cubic meters. R. No deduction in the brickwork quantity is made for openings in walls up to 0.1 m² area. S. For the measurement of excavation from the borrow pit in a fairly uniform ground, deadmen are left at suitable intervals.
For the above statements, the correct option is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 45

Open question
CENAT2 marksNeeds review
The activity details of a project are given below:
Activity
Depends on
Duration (in days)
P
--
6
Q
P
15
R
Q, T
12
S
R
16
T
P
10
U
Q, T
14
V
U
16
The estimated minimum time (in days) for the completion of the project will be

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer