GATE CE · 2017 · CE-2
Question 18: Construction Materials and Management
Give it a try, then reveal the answer to check your work.
Question 18
CE-2NAT1 markNeeds review
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate
for the 95% confidence level. The maximum time required (in days) for the completion of the project would be _________.Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2017CE-2
GATE CE 2017 · Paper 2
Civil Engineering · Original paper archive
- Section
- Section CE-2
- Question type
- Numerical answer (NAT)
- Marks
- 1 mark
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
civil engineering
GATE CE previous year questions
infrastructure
GATE CE previous year questions
structural engineering
GATE CE previous year questions
construction materials management
GATE CE previous year questions
Construction Materials and Management
GATE CE previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.