Questions 11–20 of 46. Imported answers require independent review unless marked reviewed.

Topic practice 46 questionsPage 2 of 5

Question 29

Open question
ce-1MSQ1 markNeeds review
The elements that DO NOT increase the strength of structural steel are
Your answerSelect all correct options. You can choose more than one.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 38

Open question
CE2MCQ2 marksNeeds review
A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.
P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.
Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.
Which one of the following options is CORRECT?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 47

Open question
CE2NAT2 marksNeeds review
The expression for computing the effective interest rate (

) using continuous compounding for a nominal interest rate of 5% is

The effective interest rate (in percentage) is __________ (rounded off to 2 decimal places).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
ce-1NAT2 marksNeeds review
The initial cost of an equipment is Rs. 1,00,000. Its salvage value at the end of accounting life of 5 years is Rs. 10,000. The difference in depreciation (in Rs.) computed using ‘double-declining balance method’ and ‘straight line method’ of depreciation in Year-2 is __________ (in positive integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 52

Open question
CE2NAT2 marksNeeds review
The table shows the activities and their durations and dependencies in a project.
Activity
Duration (Days)
Depends on
A
8
-
B
4
A
C
4
B
D
4
C, L
F
4
A
G
4
F
H
6
G, L
K
10
A
L
6
F, K
The total duration (in days) of the project is ________ (in integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 15

Open question
CEMCQ1 markNeeds review
In cement concrete mix design, with the increase in water-cement ratio, which one of the following statements is TRUE?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 15

Open question
CEMCQ1 markNeeds review
Which of the following equations is correct for the Pozolanic reaction?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 15

Open question
CEMCQ1 markNeeds review
Match all the possible combinations between Column X (Cement compounds) and Column Y (Cement properties):
Column X
Column Y
(i) C₃S
(P) Early age strength
(ii) C₂S
(Q) Later age strength
(iii) C₃A
(R) Flash setting

(S) Highest heat of hydration

(T) Lowest heat of hydration
Which one of the following combinations is correct?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 39

Open question
CEMCQ2 marksNeeds review
The project activities are given in the following table along with the duration and dependency.
Activities
Duration (days)
Depends on
P
10
-
Q
12
-
R
5
P
S
10
Q
T
10
P, Q
Which one of the following combinations is correct?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 53

Open question
CENAT2 marksNeeds review
The activities of a project are given in the following table along with their durations and dependency.
Activities
Duration (days)
Depends on
A
10
-
B
12
-
C
5
A
D
14
B
E
10
B, C
The total float of the activity E (in days) is ________. (in integer)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer