A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.
P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.
Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.
Which one of the following options is CORRECT?
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2024CE2
GATE CE 2024 · Paper 2
Civil Engineering · Original paper archive
- Section
- Section CE2
- Question type
- Multiple choice (MCQ)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
civil engineering
GATE CE previous year questions
infrastructure
GATE CE previous year questions
structural engineering
GATE CE previous year questions
construction materials management
GATE CE previous year questions
Construction Materials and Management
GATE CE previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.