Question 54

Open question
MNNAT2 marksNeeds review
The reliability function of a pump is given as

, where t stands for time in years. If the pump comes with a six-month warranty, the number of years for the pump to attain a reliability of 0.9 is _____.
[rounded off to 2 decimal places]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 57

Open question
MNNAT2 marksNeeds review
A coal company has three mines which transport coal to four washeries. The daily production from each mine, the demand at each washery and unit transportation cost from each mine to each washery are given in table
Mine
W1
W2
W3
W4
Supply (tonnes/day)
M1
19
30
50
10
700
M2
70
30
40
60
900
M3
40
8
70
20
1800
Demand (tonnes/day)
500
800
700
1400

The cost of initial basic feasible solution using Vogel’s approximation method is _____.
[rounded off to 1 decimal place]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 58

Open question
MNNAT2 marksNeeds review
A workship has four tasks and equal number of machines to perform the tasks. Each of the machines can perform only one of the four tasks. The estimated cost at each of the machines to complete each task is given in table
| MACHINE | T1 | T2 | T3 | T4 | |---|---:|---:|---:|---:|---:| | M1 | 10 | 40 | 60 | 30 | | M2 | 90 | 70 | 100 | 90 | | M3 | 40 | 50 | 110 | 70 | | M4 | 80 | 70 | 80 | 50 |
The total cost of optimal assignment is_____.
[rounded off to 1 decimal place]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 30

Open question
MNNAT1 markNeeds review
A safety device consists of two independent critical components

and

. The failure of any one or both of these components can cause an accident. The failure probabilities of components

and

are 0.2 and 0.1, respectively. The probability of occurrence of an accident is ______. (round off to two decimal places)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 41

Open question
MNMCQ2 marksNeeds review
A coal mining company examines the option of buying two types of dumpers with the following details.
Parameter
Type-1
Type-2
Constraints
Capital cost per dumper (in ₹ crore)
3.0
4.0
Maximum capital available for purchasing is ₹120 crore
Capacity in tonne
40
50
Minimum daily tonne to be hauled is 31,000
Daily trips for each dumper
20
20

Operating cost (in ₹) per tonne
300.0
200.0

In order to minimize the operating cost, the optimum fleet of dumpers of Type-1 and Type-2, respectively are
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 65

Open question
MNNAT2 marksNeeds review
Information on Activity-Time duration of a project is provided below
Activity
Predecessor event
Successor event
Pessimistic
Most likely
Optimistic
A
1
2
20
15
4
B
1
3
12
8
4
C
2
3
16
11
6
D
3
4
20
13
12
E
2
4
13
8
3
F
1
4
45
35
25
The expected project duration in weeks, is ______. (in integer)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 24

Open question
MNNAT1 markNeeds review
A system consists of four components connected functionally in a parallel configuration. The reliability of the individual components is 0.40, 0.60, 0.50 and 0.40. The system reliability, is________. [round off to 3 decimal places]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 50

Open question
MNNAT2 marksNeeds review
A project network consists of the following activities.
Activity
Immediate predecessors
Duration (days)
A
--
3
B
--
4
C
A, B
5
D
B
6
E
D
7
F
C, E
8
G
D
9
H
F, G
X
If the project completion time is 30 days, then the value of ‘X’, in days, is ______. [in integer]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
MNNAT2 marksNeeds review
Rate of fuel consumption

(litres per hour) of a truck varies with truck speed

, (kmph) as given below

The fuel price is Rs. 70 per litre. Other costs amount to Rs. 500 per hour. If the truck travels 100 km from a coal mine to a thermal plant, the speed of the truck, in kmph, that minimizes the total cost is ______. [round off to one decimal place]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 52

Open question
MNNAT2 marksNeeds review
A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution centre, and the associated transportation cost per tonne from factory to distribution centre are given in the Table.
Factory
D₁
D₂
D₃
D₄
Supply (tonnes/day)
F₁
20
30
110
70
600
F₂
10
0
60
10
100
F₃
50
80
150
90
1000
Demand (tonnes/day)
700
500
300
200

The initial basic feasible solution using the least-cost rule is ______. [in integer]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer