A project network consists of the following activities.
Activity | Immediate predecessors | Duration (days) |
|---|---|---|
A | -- | 3 |
B | -- | 4 |
C | A, B | 5 |
D | B | 6 |
E | D | 7 |
F | C, E | 8 |
G | D | 9 |
H | F, G | X |
If the project completion time is 30 days, then the value of ‘X’, in days, is ______. [in integer]
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2021MN
GATE MN 2021 · Paper 1
Mining Engineering · Original paper archive
- Section
- Mining Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mining engineering
GATE MN previous year questions
mining
GATE MN previous year questions
mineral processing
GATE MN previous year questions
systems engineering
GATE MN previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.