Question 31
Open questionMNNAT1 markNeeds review
The expected time (P days) and standard deviation (Q days) of the different activities (A to F) in a project are indicated in the network diagram as (P, Q). The standard deviation of the project completion time, in days, is ____________. (rounded off to one decimal place)

Network diagram activity labels and nodes: A (12, 0) from 1 to 2; B (23, 4) from 1 to 3; C (15, 1) from 2 to 4; D (18, 2) from 4 to 5; E (27, 3) from 3 to 6; F (6, 2) from 5 to 6.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 42
Open questionMNMCQ2 marksNeeds review
A shovel needs to be selected from four models of different capacities, S1 to S4, for loading of dumpers. The operational data for the shovel-dumper combination are provided. The mean arrival rate of the dumpers at the loading point is 5 per hour and the waiting cost of dumper is ₹ 200 per hour. The inter-arrival time of dumpers and loading time of shovel follows exponential distribution. Ignoring the shovel hiring cost, the shovel type that will have minimum total cost (waiting and operating cost) is
Model | Operating cost of shovel (₹ per hour) | Mean loading rate of shovel (number of dumpers per hour) |
|---|---|---|
S1 | 80 | 8 |
S2 | 85 | 9 |
S3 | 90 | 10 |
S4 | 100 | 11 |
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 47
Open questionMNNAT2 marksNeeds review
A mine workshop needs to assign 4 jobs to 4 service engineers. The cost for performing a job by an individual service engineer is given. A typical job can be assigned to only one service engineer. If the service engineer S1 cannot perform the job J3, and S3 cannot perform the job J4, the optimal cost for completion of jobs is ____________. (answer in integer)
Service Engineer | J1 | J2 | J3 | J4 |
|---|---|---|---|---|
S1 | 50 | 50 | --- | 20 |
S2 | 70 | 40 | 20 | 70 |
S3 | 90 | 30 | 50 | --- |
S4 | 70 | 20 | 60 | 30 |
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 37
Open questionMNMCQ2 marksNeeds review
Following information are given for three mines of a company receiving explosives from three suppliers.
Explosive suppliers | Mine-1 | Mine-2 | Mine-3 | Supply capacity (tonne) |
|---|---|---|---|---|
Supplier - S | 10 | 15 | 50 | 2500 |
Supplier - O | 5 | 2 | 100 | 2500 |
Supplier - I | 30 | 40 | 20 | 3000 |
Explosive demand (tonne) | 1000 | 2000 | 500 | |
Considering the initial basic feasible solution of this transportation problem, using North-West corner method, the transportation cost of explosives supplied to the company, in Rs., is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 19
Open questionMNMCQ1 markNeeds review
In a M/M/1 system, the inter-arrival time of dumpers to a shovel follows exponential distribution with a mean arrival rate of 9 dumpers per hour. The service time of the shovel follows exponential distribution with a mean service rate of 12 dumpers per hour. The probability that exactly one dumper is available to the shovel is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 20
Open questionMNMCQ1 markNeeds review
A project network with the sequence of five activities is shown.

The crashing costs of activities are
Activity | A | B | C | D | E |
|---|---|---|---|---|---|
Duration (week) | 5 | 6 | 8 | 3 | 4 |
Crashing cost per week (lakh INR) | 4.0 | 2.5 | 2.0 | 3.0 | 4.0 |
If the project is crashed by one week, the increase in project cost, in lakh INR, is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 36
Open questionMNMCQ2 marksNeeds review
Data from two production faces of an open pit iron ore mine are given.
Item description | Face 1 | Face 2 |
|---|---|---|
Maximum production capacity (tonne/day) | 1600 | 2000 |
Fe (%) | 63 | 58 |
Production cost of ores (in INR/tonne) | 1500 | 1200 |
Ores from two different faces are blended and supplied with Fe grade not less than 60 %. Based on the demand, the combined production is limited to a maximum of 2500 tonne/day. If the selling price of blended iron ores is INR 4500 /tonne, the optimal production from two faces in tonne/day, for maximizing the profit, respectively are
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 46
Open questionMNNAT2 marksNeeds review
A transportation system for carrying ore from stock pile to railway siding through an ore bin is shown. The time between failure of each conveyor belt follows an exponential distribution with mean time between failure of 700 hours. The system is considered to be a ‘success’ if ore transports from stock pile to siding by any combination of belts. The reliability of the system for 350 hours of continuous successful operation is _____. (round off up to 2 decimals)

Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 19
Open questionMNMCQ1 markNeeds review
A linear programming problem is given as:
Maximize
Subject to:
The problem hasYour answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 22
Open questionMNMCQ1 markNeeds review
In project scheduling techniques, the CORRECT statement is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer