Data from two production faces of an open pit iron ore mine are given.
Item description | Face 1 | Face 2 |
|---|---|---|
Maximum production capacity (tonne/day) | 1600 | 2000 |
Fe (%) | 63 | 58 |
Production cost of ores (in INR/tonne) | 1500 | 1200 |
Ores from two different faces are blended and supplied with Fe grade not less than 60 %. Based on the demand, the combined production is limited to a maximum of 2500 tonne/day. If the selling price of blended iron ores is INR 4500 /tonne, the optimal production from two faces in tonne/day, for maximizing the profit, respectively are
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2024MN
GATE MN 2024 · Paper 1
Mining Engineering · Original paper archive
- Section
- Mining Engineering
- Question type
- Multiple choice (MCQ)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mining engineering
GATE MN previous year questions
mining
GATE MN previous year questions
mineral processing
GATE MN previous year questions
mine planning
GATE MN previous year questions
systems engineering
GATE MN previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.