Question 36

MNMCQ2 marksNeeds review
Data from two production faces of an open pit iron ore mine are given.
Item description
Face 1
Face 2
Maximum production capacity (tonne/day)
1600
2000
Fe (%)
63
58
Production cost of ores (in INR/tonne)
1500
1200
Ores from two different faces are blended and supplied with Fe grade not less than 60 %. Based on the demand, the combined production is limited to a maximum of 2500 tonne/day. If the selling price of blended iron ores is INR 4500 /tonne, the optimal production from two faces in tonne/day, for maximizing the profit, respectively are
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2024MN

GATE MN 2024 · Paper 1

Mining Engineering · Original paper archive

Section
Mining Engineering
Question type
Multiple choice (MCQ)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mining engineering

GATE MN previous year questions

mining

GATE MN previous year questions

mineral processing

GATE MN previous year questions

mine planning

GATE MN previous year questions

systems engineering

GATE MN previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.