Question 20

MNMCQ1 markNeeds review
A project network with the sequence of five activities is shown.
Diagram for Mining Engineering question 20

The crashing costs of activities are
Activity
A
B
C
D
E
Duration (week)
5
6
8
3
4
Crashing cost per week (lakh INR)
4.0
2.5
2.0
3.0
4.0
If the project is crashed by one week, the increase in project cost, in lakh INR, is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2024MN

GATE MN 2024 · Paper 1

Mining Engineering · Original paper archive

Section
Mining Engineering
Question type
Multiple choice (MCQ)
Marks
1 mark

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mining engineering

GATE MN previous year questions

mining

GATE MN previous year questions

mineral processing

GATE MN previous year questions

systems engineering

GATE MN previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.