Question 53: Mine Planning
Give it a try, then reveal the answer to check your work.
Question 53
MNNAT2 marksNeeds review
The grade-tonnage distribution for the ultimate pit of a mine is given below.
Cu grade (%) | Cumulative million tonnes below the grade |
|---|---|
0.1 | 0 |
0.4 | 15.0 |
0.5 | 17.0 |
0.6 | 18.0 |
0.7 | 19.0 |
0.9 and above | 23.0 |
The mill cut-off grade is 0.5 % Cu. The annual mining capacity (ore + waste) is 4.5 million tonne and milling capacity is 1.0 million tonne. Excavation is planned in such a way that either of the mine or the mill runs at full capacity throughout. The planned life of the mine, in years, is ______. [round off to one decimal place]
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2021MN
GATE MN 2021 · Paper 1
Mining Engineering · Original paper archive
- Section
- Mining Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mining engineering
GATE MN previous year questions
mining
GATE MN previous year questions
mineral processing
GATE MN previous year questions
mine planning
GATE MN previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.