Question 49

Open question
MTMSQ2 marksNeeds review
Identify the INCORRECT statement(s)
Your answerSelect all correct options. You can choose more than one.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
MTNAT2 marksNeeds review
Molten steel at 1873 K weighing 100 metric tons is desulfurized using 1250 kg of synthetic slag by equilibration. If the sulfur content in the steel is reduced from 0.015 mass% to 0.0025 mass%, the desulfurizing index is ______ (round off to the nearest integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 35

Open question
MTMCQ2 marksNeeds review
Match the terms (in Column I) with the unit process (in Column II)
Column I Column II (P) Submerged Entry Nozzle 1. Ladle Furnace (Q) Electric Heating 2. Continuous Casting (R) Raceway Zone 3. LD Converter (S) Oxygen Lancing 4. Blast Furnace
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 49

Open question
MTNAT2 marksNeeds review
1000 kg of liquid steel containing 0.03 wt.% S needs to be desulphurized using a slag to bring the sulphur content down to 0.015 wt.%. The quantity of slag needed is ______ kg (round off to the nearest integer).
Assume:
Thermodynamic equilibrium
No sulphur in the slag prior to desulphurization treatment
Given the equilibrium sulphur partition ratio between slag and steel,

.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 9

Open question
MTMCQ1 markNeeds review
The correct sequence of steelmaking operations is [BOF: Basic Oxygen Furnace; LF: Ladle Furnace; VD: Vacuum Degassing; CC: Continuous Casting].
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 27

Open question
MTMCQ2 marksNeeds review
Match the injection metallurgy techniques in Column I with the corresponding objectives in Column II.
Column I: Injection metallurgy techniques (P) Aluminium wire feeding (Q) Calcium treatment (R) Argon rinsing (S) Lime powder injection
Column II: Objectives
Inclusion modification
Mixing of liquid steel
De-sulphurization
Deoxidation
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 5

Open question
MTMCQ1 markNeeds review
Arrange the following in the correct sequence of operations in an integrated steel plant:
i. Basic Oxygen Furnace (BOF) ii. Blast Furnace (BF) iii. Ruhrstahl Heraeus Degasing Process (RH) iv. Ladle Furnace Process (LF)
Your answerChoose one option.

Log in to check the answer