GATE MT · 2018 · MT
Question 5: Primary steel making
Give it a try, then reveal the answer to check your work.
Question 5
MTMCQ1 markNeeds review
Arrange the following in the correct sequence of operations in an integrated steel plant:
i. Basic Oxygen Furnace (BOF)
ii. Blast Furnace (BF)
iii. Ruhrstahl Heraeus Degasing Process (RH)
iv. Ladle Furnace Process (LF)
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2018MT
GATE MT 2018 · Paper 1
Metallurgical Engineering · Original paper archive
- Section
- Metallurgical Engineering
- Question type
- Multiple choice (MCQ)
- Marks
- 1 mark
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
metallurgy
GATE MT previous year questions
materials science
GATE MT previous year questions
materials engineering
GATE MT previous year questions
primary steel making
GATE MT previous year questions
iron steel making
GATE MT previous year questions
Iron and steel making
GATE MT previous year questions
secondary steel making
GATE MT previous year questions
basic oxygen furnace
GATE MT previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.