How to practice Facility Design

Attempt a question, record the concept and assumptions, then check the available answer. Rework mistakes after revising the relevant concepts. Topic tags can overlap; review the question context.

Questions 1–10 of 15. Imported answers require independent review unless marked reviewed.

Topic practice 15 questionsPage 1 of 2

Question 64

Open question
PINAT2 marksNeeds review
Consider an assembly line producing an item through a process involving three activities in the following order: cutting, welding, and polishing. There are three workers available: one is assigned only for cutting, one is assigned only for welding, and one is assigned only for polishing.
The activity time per item is given in the table.
Assuming that the process is running in steady state, the total number of items coming out of the assembly line in six hours is _____ (in integer).
Note: Assume that workers, items, and machines/tools are available as and when needed.
Activity name
Cutting
Welding
Polishing
Activity time/item (in minutes)
30
40
25

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 49

Open question
PINAT2 marksNeeds review
A product has to be manufactured in a single-line layout by carrying out the six tasks in a sequence. The time (in minute) of the six sequential tasks are 37, 8, 19, 34, 36 and 17. These tasks cannot be further sub-divided. For minimizing the cycle time, the number of stations to be used is________. (Answer in integer)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 19

Open question
PIMCQ1 markNeeds review
The following layout of four departments P, Q, R and S is provided as input to CRAFT (Computerized Relative Allocation of Facilities Technique). Which one of the following department pairs cannot be considered for exchange in CRAFT?
Diagram for Production and Industrial Engineering question 19

Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 62

Open question
PINAT2 marksNeeds review
An assembly line consists of three work stations (S1, S2 and S3) in series to assemble a toy. The times required to perform tasks at these stations are 6, 4 and T minutes, respectively. If the efficiency of the assembly line in the steady state is 75%, then the maximum value of T (in minutes) is ________. (Answer in integer)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 45

Open question
PIMCQ2 marksNeeds review
There are four locations (P, Q, R, S) and four factors to be considered for setting up a facility. The scores (on a scale of 0 to 10, with 10 being the maximum) for the given locations and the weight assigned to each factor are given as
Factor
Weight
P
Q
R
S
Availability of raw material
0.4
6
8
5
4
Availability of skilled labor
0.3
7
4
10
6
Infrastructure
0.2
8
3
10
8
Proximity to market
0.1
10
8
7
5
The best location for setting up the facility is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 22

Open question
PIMCQ1 markNeeds review
Match the types of layout with the types of production.
Type of layout: P Process layout; Q Product layout; R Fixed position layout. Type of production: 1 Job production; 2 Batch production; 3 Mass production.
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 4

Open question
PIMCQ1 markNeeds review
Which one of the following is an improvement type heuristic algorithm for computerized layout design technique?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 29

Open question
PIMCQ2 marksNeeds review
A retail chain company has identified four sites A, B, C and D to open a new retail store. The company has selected four factors as the basis for evaluation of these sites. The factors, their weights, and the score for each site are given in the following table.
Factor
Factor weight
Score for site (out of 100): A
B
C
D
Average community income
0.4
60
70
80
50
Demand growth potential
0.1
30
80
50
40
Proximity to existing store
0.3
50
10
40
60
Availability of public transport
0.2
40
30
40
20
The site that should be selected to open the new retail store is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 54

Open question
PINAT2 marksNeeds review
A company has to perform five tasks (P, Q, R, S and T) to make an assembly. Task times and immediate predecessor of the tasks are listed below. If an assembly line is designed to obtain the maximum output rate, the efficiency of the line in % is ____________.
Task
Task time (Seconds)
Immediate predecessor(s)
P
20
-
Q
25
P
R
10
Q
S
15
Q
T
25
R, S

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 16

Open question
PIMCQ1 markNeeds review
REL chart is used in
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer